Project Description
Project will replace the existing two-lane Flamingo Boulevard from 776 to a point north of Edgewater Drive and the existing remaining section of two-lane Edgewater Drive from Midway Boulevard to Collingswood Boulevard with a new four-lane roadway. The project will also connect Flamingo Boulevard from its southernmost curve to the intersection of Edgewater Drive and Collingswood Boulevard, creating a new alignment for the roadways. Additionally, intersection improvements at 776 and Flamingo Boulevard will be included.
The project is split into 3 phases, identified as phases 3, 4, & 5. The design will include all three phases and the construction will be multiphase.
项目位置
Flamingo Boulevard from 776 to a point north of Edgewater Drive, connecting Flamingo Boulevard from its southernmost curve to the intersection of Edgewater Drive and Collingswood Boulevard, including Edgewater Drive from Midway Boulevard to Collingswood Boulevard.
最新的更新
Johnson Engineering has been selected as the design firm for this project. The county is working with the firm to design all project phases. The design and permitting portion is expected to take about two and half years from the notice to proceed date of March 1, 2022.
- 95% of field survey work has been completed.
- Protected species and wetlands evalution in process.
- 95% of geotechnical field work has been completed.
- 90% roadway plans are in progress.
- 90% bridge plans are in progress.
- 90% utility plans are in progress.
- Property acquisition in progress. Including work leading up to imminent domainn process.
- The process has started to obtain the necessary SWFWMD permit.
- Coordination to resolve outside utility conflicts is ongoing.
- FDOT Lap project review is in progress.
- Agency permitting review in progress.
预算
阶段 | 成本 |
---|---|
设计 | $5,068,415 |
2014 Sales Tax Extension for the design of phases 3, 4, & 5.
2020 Sales Tax Extension for the construction of phase 4, in the future.
时间表
阶段 | Estimated Start Date | Forecast Completion | 实际完成 |
---|---|---|---|
设计 Development | 03/01/2022 | 09/30/2024 | |
建设 | 11/01/2024 |
项目阶段
Planning and Project Approval
最后一次更新
05/02/2024
项目经理
扎克Patchell
公共关系
特蕾西·多尔蒂
Email 公共关系
项目数量
c412102
Sponsor Department
公共工程
设计 Engineer/Architect
Johnson Engineering
建设 Contractor
TBD